TRAFFIC ALERT
TRAFFIC ALERT
Caltrans
Wednesday, March 06, 2019

U.S. HIGHWAY 50 MOSQUITO ROAD BRIDGE UNDERCROSSING

SCHEDULE

Work will start Monday, April 1 at 12:01 a.m. until Friday, April 12 at 11:59 p.m. for a total of 12 days, working 24 hours a day. Highway 50 will be reduced to one lane in each direction during this time. 

SCOPE OF WORK

Remove asphalt concrete bridge deck surface, remove concrete deck surface, drill and bond dowels, replace concrete deck surface with reinforced concrete, and replace concrete barrier. Once bridge work is finished, a polyester overlay of the bridge deck and permanent striping will be completed.

RAMP CLOSURES

The Mosquito Road on-ramp to westbound Highway 50 will be closed during construction.  The eastbound 50 off-ramp to Broadway will be closed until approximately Thursday, April 4.  The westbound 50 off-ramp to Mosquito Road will remain open.

EXPECTED DELAYS

Motorists should expect delays of up to 45 minutes Monday through Thursday, and significantly longer eastbound on Friday, April 5 and westbound on Sunday, April 7.  Motorists are encouraged to use alternate routes and avoid peak travel times.